Resource Management Archiving and assignments
Hi everyone,
What is the expected behaviour of users' assignments when a project is archived in RM ? I assumed assignments (especially current and future) would be removed or stopped counting towards the users allocation heatmap. Seems like this does not happen.
Answers
-
Hi @joaolima
I checked in with our Support team and I see you raised a ticket internally with us, thank you!
If anyone else has the same question, there have been reports of instances where ongoing or future assignments within a project are not affected by archiving. This is currently being investigated but we do not have an ETA for when it may be resolved.
For now, if the project is ‘Disconnected’ from within Resource Management's (RM's) Integrations Panel before the project is archived in RM, the issue doesn’t occur.
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.1K Get Help
- 414 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives