Sheet summary to populate date in sheet
Hi all,
I'm currently creating a template to monitor store closures and need some support in setting up a way to populate a date from the sheet summary. The end goal is to when in use, to be able to populate the date for the activity to start and able to flag any outstanding points after 30 days.
We are able to populate the parent task referencing the sheet summary, referencing the store name and number.
We need help with how to make the start date in the plan pull from the sheet summary
Answers
-
If you are using dependencies, you cannot use formulas in any column being used by the dependency settings.
-
Thanks @Paul Newcome for getting back to me.
@Martha Hemingway does this help with what we are trying to achieve?
-
Thanks @Paul Newcome! What you're saying is we'd have to remove the dependencies in the project settings for the formula to populate in the grid from the sheet summary. Is that correct?
Ideally we are trying to create a template of a standard project plan where we can give an easy way for 2 initial "start dates" of tasks to be documented. I was hoping we could train using the Sheet Summary fields to enter those 2 critical dates that would complete out the milestone kicking off the remaining tasks tied to the milestone. Would you have any other suggestions?
Thanks!!!
-
That is correct. Formulas cannot be used in columns that are being used by the dependency settings. My suggestion would be to train them on exactly where to enter the start date within the project plan itself. If you set up the various durations and predecessors, a single date entered should populate the rest of the project plan.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 437 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives