Manpower Projection Formula
I have multiple schedules for different projects with the same base information:
Task Name (Primary)
Start Work Date
End Work Date
Duration (Dependencies are enabled)
Manpower Needed
Many tasks have durations that overlap with other tasks.
I want a separate manpower projection sheet that tells me each day what the total manpower would be needed so I can forecast months/years in advance how many people I would need to do my jobs.
Example:
5/1 - 5/3: Total Manpower Needed = 10
5/2 - 5/4: Total Manpower Needed = 6
5/1 Total Manpower Needed = 10
5/2 Total Manpower Needed = 16
5/3 Total Manpower Needed = 16
5/4 Total Manpower Needed = 6
I have been trying the =SUMIFS formula but I can't figure out how to calculate the manpower needs between the SWD (Start Work Date) & EWD (End Work Date)
Current Formula: =SUMIFS({CMH076 - Active Schedule Estimated Manpower}, {CMH076 - Active Schedule SWD}, SWD@row)
I really appreciate any help!
Answers
-
- You can calculate the duration between the SWD and EWD.
- In order to calculate the Manpower, you can find the average time one worker takes to complete the task in hours.
Formula: CEILING(Duration/ (Hours_per_worker *24), 1)
I am anticipating, if this would work.
Thanks,
Deepanshu Sharma
-
Sharma,
Thank you for the quick response. This formula did not work for me though.
Hours worked or to complete a task does not matter in this application. I strictly just need to know on any given day throughout the year how much manpower I need. -
don't forget that with sumifs you can have multiple criteria:
for manpower on a specific date try something like this: =SUMIFS({manpower},{startDate},dateYouCareAbout@row,{endDate},dateYouCareAbout@row)
For manpower between two different dates, this:
=SUMIFS({manpower},{startDate},">=" + startDateYouCareAbout@row,{endDate},"< =" + endDateYouCareAbout@row)
-
Jgorsich,
Using this formula:
=SUMIFS({Labor Schedule Range 1}, {Labor Schedule Range 2,">=" + SWD@row, {Labor Schedule Range 3},"<=" + EWD@row))
I am getting an unparseable.
I would like to clarify what I am trying to do.
I have multiple tasks with various durations. At some point, most tasks duration overlaps with another. I need to project out on any given day what my total labor needs would be for that day.In the snip-it below I have manually inputted the numbers to show what they should be for each day due to the overlap in tasks.
Below that I had copied out the dates again and showed the formula I am using.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 437 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!