Resource Management License Needed to Access Slide Out?
Options
Answers
-
To create the connection between a Smartsheet project sheet to a Resource Management project plan, you must be the following:
- a licensed Smartsheet user
- the sheet owner or admin
- a Resource Management portfolio editor, project editor or resourcing admin
See:
However if the panel integration has already been configured/set up for that sheet, then your collaborators in Smartsheet will be able to see it as well.
- Resourcing Administrators, Portfolio Editors, and People Schedulers can update assignments in Resource Management.
- Owners, Admins, and sheet Editors can update assignments in Smartsheet.
See:
If this hasn't answered your question, it would be useful to have a specific scenario detailed - then we can confirm what that user can/cannot do. 🙂
Cheers,
Genevieve