  • Tony Platts
    Tony Platts ✭✭✭✭✭

    This is now completely failing for me because both Chrome and Edge are limited to 4gb per tab. Just looking at the data gives me the Aww Snap - Out of Memory error message.

    I'm also noticing that the automated overnight report is failing with the status message "Data refresh failed on 8 Oct 2024 at 17:59"

    All im trying to pass over is a list of all of the teams projects with a total incurred hours, and forecasted hours, in a way that we can call it from a sheet.

  • Tony Platts
    Tony Platts ✭✭✭✭✭

    Just as an update, I've now been advised that I need to pay for Datamesh to resolve the issues. So, let's look at the timeline here.

    1. Smartsheet announces new functionality.
    2. User sets up automated report.
    3. Updated report starts failing.
    4. Recommendation is to use another paid product.

    Not exactly a fantastic experience.

  • Erin Horiuchi Green
    Erin Horiuchi Green ✭✭✭✭✭

    @Tony Platts If you could provide me a little bit more clarity on your Smartsheet foundation, I might be able to assist you on a solution.

    1) Smartsheet Grid with Resource Management enabled
    2) …

    Erin Horiuchi Green, MBA, LSSYB, PSMI
    Process Manager
    Syneos Health

    Please kindly like ❤️, upvote ⬆️ and/or mark ✅ any of my contributions that have provided value.

    Core App and Project Managment Certified 🚀