Negative Float

Can anyone tell me what would have to change in the plan below for me to end up with a negative float?
It seems that if I add any duration to Activities B through L (which I would expect would create a negative float), the end date for the final task (Activity M) simply gets pushed out to compensate. No Negative Float results.
Appreciate the help.
Answers
-
You would be able to use Baselines with GANTT view to show for the days that you are over / under in order to see the total variance (negative float) for the project.
Additionally, you would be able to create a new column for float, and tract that using the totalfloat function
If my answer helped you, please be sure to mark it as Accepted to help future learners locate the information.
Always happy to work through questions or concerns!
-
Thank you, Colleen. Appreciate it!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 67.3K Get Help
- 462 Global Discussions
- 156 Industry Talk
- 508 Announcements
- 5.4K Ideas & Feature Requests
- 85 Brandfolder
- 156 Just for fun
- 81 Community Job Board
- 518 Show & Tell
- 35 Member Spotlight
- 3 SmartStories
- 307 Events
- 35 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!