Negative Float
Can anyone tell me what would have to change in the plan below for me to end up with a negative float?
It seems that if I add any duration to Activities B through L (which I would expect would create a negative float), the end date for the final task (Activity M) simply gets pushed out to compensate. No Negative Float results.
Appreciate the help.
Answers
-
You would be able to use Baselines with GANTT view to show for the days that you are over / under in order to see the total variance (negative float) for the project.
Additionally, you would be able to create a new column for float, and tract that using the totalfloat function
Smartsheet Community Champion and Ambassador
If my answer helped you, please be sure to mark it as Accepted to help future learners locate the information.
-
Thank you, Colleen. Appreciate it!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!