Need a formula to add/subtract calendar days to a date to create a new date
Smartsheets seems to be defaulting to adding/subtracting business days, but I want the formula to use calendar days instead, how do I do this?
My current formula is =[Planned End Date]1 - 195. But I want it to be 195 calendar days, not business days. How do I change it to be calendar days?
Answers
-
Doing it that way should be calendar days. Can you provide a screenshot of a few entries where this is calculating business days instead of calendar days?
-
Okay yes, you're right! 3/20/24 IS 195 calendar days prior to 10/1/24, and is 140 business days prior to 10/1/24, not considering holidays, so I think I'm good. I just have to remember duration will calculate my planned end date using business days, not calendar days.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.4K Get Help
- 396 Global Discussions
- 213 Industry Talk
- 448 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 133 Just for fun
- 56 Community Job Board
- 454 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 293 Events
- 35 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!