Hi!
Could you add the ability to enter in elapsed days (non-working days) into the predecessor field? This would be similar to the e#d in duration. Thank you!!
Kind regards,
Helena
Sign in to see the current vote count, add your own vote, or leave a comment.
Predecessor Field Enhancement to Support Elapsed Days. There is a critical need for Smartsheet to incorporate the ability to link from working days to elapsed days within the Predecessor Field. This enhancement is not just a convenience but a necessity for comprehensive project management.
The integration of elapsed days with predecessors is a feature that has seen consistent demand over the years. Its absence significantly hampers our ability to accurately track project timelines, especially in our industry where work progresses continuously across both working days and weekends and holidays.
Please seriously consider the long-term benefits and user satisfaction that this enhancement will bring.
Community, if you don't have the time to leave a comment please vote up the most applicable existing comment.
Please add this feature! It would be incredibly helpful!
+1 for this feature request, very important feature.
Extremely important feature! There are many threads with this topic, but this seems most recent so hoping I can bump it here.
My constant headache is that I manage many tech projects with weekend migrations - but migrations always have go/no-go dependencies, so I want to keep my predecessors in place in case anything shifts upstream.
If a row has no dependencies, using elapsed time to override non-working days works just fine. But if the row has a predecessor, it's impossible to force the START date to begin on a non-working day.
PLEASE FIX THIS!!
In the Community discussions I see 4 years of comments on multiple threads asking to add the use of elapsed time in predecessors - why hasn't this been implemented yet? Even when both the predecessor & the active task both have a elapsed time Duration, it still calculates the lag time in working days. So frustrating when my project is based on dependencies between different groups that have different working hours.
I rely heavily on Smartsheet’s Document Generation. However, this workflow is currently dependent on having photos stored inside cells, since row attachments alone cannot be used directly in document generation.. If Smartsheet allowed attachments to be displayed as thumbnails in cells (as a reference), document generation…
I’d like to see user analytics for WorkApps. I’ve checked the user report available in the Collaborator Pack, but it only shows how many times someone has clicked into the WorkApp each month. I’d like to know: Which resources (dashboards, sheets, forms, etc.) are getting the most traffic? Where are people spending their…
Hi There, I would like to propose that Smartsheet considers the email subject header that is received from a Smartsheet notification from a form or sheet. Currently, because not everyone in my company has Smartsheet, let alone a Smartsheet log-in, we need to send show the name of the owner of the sheet, that appears on the…