templates
I recently created a project from the templates provided - the 'Ticketing system' one. How would I go about changing the 'duration' column from days to hours? We report on an hourly basis for our projects but it's a locked field and when I edit it, it doesn't give me the option to change the type.
Thanks in advance!
Answers
-
Duration is a locked field type because it is being used for the gantt chart in settings. You could create a separate "Hourly Duration" column and then hide the other column. Would this work?
Michelle Choate
michelle.choate@outlook.com
Always happy to walk through any project you need help with!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.4K Get Help
- 424 Global Discussions
- 221 Industry Talk
- 462 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 144 Just for fun
- 59 Community Job Board
- 463 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives