Why is PROJECTED COMPLETION DATE Column Autopopulating with Date After Date Assigned

One of my PMs has noticed that the date in the PROJECTED COMPLETION DATE column on an assignment tracker is autopopulating with a date one day after the DATE ASSIGNED date. We have dependencies turned on to utilize Resource Management functionality with the sheet, but aren't using the PREDECESSORS column to capture any information. Is there a way to remove this date autopopulation without disabling the dependencies?

Tags:

Answers