Need the minimum start date for projects, what's the formula?
I'm trying to get the formula for the min start date based on the project number. So in the chart below the minimum start date for project 1 should be 11/5/24.
Best Answer
-
@Amy Merrill Use this formula in the Min Start column.
=MIN(COLLECT([Start Date]:[Start Date], Project:Project, Project@row))
Isis Taylor
🎓️ Core App and Project Management Certified 🏅
🌟Peer Connect, Mobilizer, and Early Adopter Program
Business Analyst Senior
Answers
-
@Amy Merrill Use this formula in the Min Start column.
=MIN(COLLECT([Start Date]:[Start Date], Project:Project, Project@row))
Isis Taylor
🎓️ Core App and Project Management Certified 🏅
🌟Peer Connect, Mobilizer, and Early Adopter Program
Business Analyst Senior
-
That worked! Thank you so much Isis!
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.5K Get Help
- 433 Global Discussions
- 152 Industry Talk
- 494 Announcements
- 5.3K Ideas & Feature Requests
- 85 Brandfolder
- 155 Just for fun
- 77 Community Job Board
- 506 Show & Tell
- 34 Member Spotlight
- 2 SmartStories
- 307 Events
- 37 Webinars
- 7.3K Forum Archives
Want to practice working with formulas directly in Smartsheet?
Check out the Formula Handbook template!
Check out the Formula Handbook template!