Need the minimum start date for projects, what's the formula?
I'm trying to get the formula for the min start date based on the project number. So in the chart below the minimum start date for project 1 should be 11/5/24.
Best Answer
-
@Amy Merrill Use this formula in the Min Start column.
=MIN(COLLECT([Start Date]:[Start Date], Project:Project, Project@row))
Isis Taylor
🎓️ Core App and Project Management Certified 🏅
🌟Peer Connect, Mobilizer, and Early Adopter Program
Business Analyst Senior
Answers
-
@Amy Merrill Use this formula in the Min Start column.
=MIN(COLLECT([Start Date]:[Start Date], Project:Project, Project@row))
Isis Taylor
🎓️ Core App and Project Management Certified 🏅
🌟Peer Connect, Mobilizer, and Early Adopter Program
Business Analyst Senior
-
That worked! Thank you so much Isis!