I have an extensive project plan with 250 sub-tasks, which is maintained separately for every client.
As 95% of the task list for every client rollout, and the time allocated to every task remains the same; is it possible to automate this process i.e. I simply enter a start date for the project, and each and every task in the project plan automatically populates a start and end date for a task? (this is ofcourse based on whether one can pre-assign/define the days allocated to each task in the template).