Templatizing
I have an extensive project plan with 250 sub-tasks, which is maintained separately for every client.
As 95% of the task list for every client rollout, and the time allocated to every task remains the same; is it possible to automate this process i.e. I simply enter a start date for the project, and each and every task in the project plan automatically populates a start and end date for a task? (this is ofcourse based on whether one can pre-assign/define the days allocated to each task in the template).
Comments
-
Yes, if you connect all tasks using predecessors/successors, you enter one date, and the rest populate.
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives