Calculating a Date Based on a Future Date
Hello,
I am trying to use my smart sheet for a event plan. I have the date of the event at the end of the month, but I'd like the fill in the dates of emails and meetings that will be held before hand.
Events Dates 1/25/18 to 1/27/18
Meeting 60 days before
Email #1 2 weeks before
Email #2 2 days before
Any help would be greatly appreciated!
-Danielle
Comments
-
Are you using dependencies? If so, you can set up the sheet to automate the dates by making rows dependent on previous rows.
Here is more information on dependencies: https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
Using Formulas instead of predecessors and Dependencies.
If you created your own sheet and are not using predecessors or a template that is set up with dependencies you can also use formulas to set the dates you want. Note which column and row the final end date is on... i.e. DueDate10 then you can use this formula in your row for the Meeting Date. =DueDate10-60
Using Calendar Days
That will give you 60 days before the due date. Note: The formula needs to be put in a date column so use the same column as the original due date. To calculate the others, you can use the same formula and subtract the number of days.
Using Workdays
If you want to use workdays instead of calendar days (workdays ignore weekends) then use =Workday(DueDate10, -60) to calculate 60 workdays from the due date.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives