Hello all,
Can anyone tell me why when importing an exported plan from Smartsheet into MS Project it places some of the %complete to 99% when it should be 0%? It is really annoying. I am currently trying it on a template plan.
Thank you in advance.
Hello Andresp,
The issue you are describing is a known bug with no currently known workaround. I have reported this instance to our development team for tracking.
Thanks!SchiffSmartsheet Support
Hi, "Fields marked with an asterisk (*) are required." is the very first line in the body of every form I create. I don't remember seeing it before (unless you missed filling out a required field; then you would see the message). Is there a way to turn it off or change it? None of my forms are in English so the message is…
I have a sheet that I pull into a report. The report I then want to use to make a stacked bar chart and put into a dashboard if I can. The columns I am trying to make into a stacked chart are: Lead, project and phase. The issue is that there are several leads and I need the stacked bar chart to show in different colors for…
I have a dynamic view setup for a dashboard that has NO restrictions And on the Sharing tab, I have a Group that I created as the additional share access to the view But the individuals in the Group still cannot see the data from the dashboard. Am I missing something? Because when I share the view to them individually…