I have a task in SS on a Gantt chart sheet, Start date 21/08/2015 and 2d duration.
When I export this sheet to a google Cal the corresponding event in a 1 day event with the following Description:
NOTE: This event was published from the Smartsheet named "HL Callendar". Changes you make in Google Calendar will not be reflected in Smartsheet. To edit, click the Smartsheet icon, or go to https://app.smartsheet.com/b/editrow?lx=-****.
Is this a know issue or am I doing something wrong?
Thx