I am building a production scheduler with a built in calculator where by the operator can adjust the labour allocation to test the duration output.
My problem is Smartsheet won't allow durations to be edited by way of a formula.
Also I am wanting the variables to be as follows:
Completion Date - Constant (fixed) Variable
Duration - Dependant Variable (dependant on formula input)
Start Date - Output (calculated backwards, completion date less the duration)
I can quite easily achieve this by disabling dependencies however I need dependencies to include and programme sub-deliverable and subsequent tasks.
If you wish to contact please send to huxley@apollofabrication.com.au not to accounts.
Thanks,
Huxley