Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Update a Status Column when % Complete
I have two columns in my Project Sheet which should always be in sync. I want my team to only update the "% Complete" column as they make progress on tasks, but I would like to see the "Status" column update automatically.
- If % Complete is = 0%, then Status should be "Not Started"
- If % Complete is > 0% AND < 100%, then Status should be "In Process"
- If % Complete is = 100%, then Status should be "Completed"
Would you help me define this?
Comments
-
You can use an IF statement in the "Status" column, such as:
IF([% Complete]1 = 0, "Not Started", IF([% Complete]1 = 1, "Complete", "In Progress"))
-
Try this:
=IF([% Complete]6 = 0, "Not Started", IF(AND([% Complete]6 > 0, [% Complete]6 < 1), "In Progress", IF([% Complete]6 = 1, "Completed")))
-
I just saw this response after created a discussion asking the same thing.
Questions:
If someone manually enters the status it overrides the formula. Will locking the column prevent this?
How can you apply the formula to a long column with multiple parent tasks?
-
Hi Stan - Locking columns will prevent Editors from changing the value in the locked column. Admins and the sheet Owner can still edit locked columns.
For your second question - are you asking how to copy this formula down an entire column? You can drag fill the formula by clicking and dragging the bottom right of the formula cell or use the Copy Down keyboard shortcut. Highlight the range of cells you want to copy the formula to, with the first cell in the range containing the formula. Press CTRL + D to copy down the formula.
-
What would my formula look like if I wanted to do the reverse of this? For example:
If Status = "Complete" then % Complete is 100%
If Status = "Not Started" then % Complete is 0%
-
gnarsted,
Formula would look like this:
=IF([Status]@row = "Complete", "100%", (IF([Status]@row = "Not Started", "0%", "")))
Currently this is set to return a blank cell if the Status does not meet any of these criteria. If you want to change this, simply add whatever you would like into the last section which is currently , "")))
Also the @row instead of calling out the row number allows you to copy paste through multiple sections without having to rework the formula.
-
I am using the card view as a Kanban board. When someone drags and drops a card into the completed lane, I want the Completed Date to update with the date the status changed to "completed."
I don't want to lose the drag and drop functionality because that is what makes it so user friendly (if they have to enter the date, they would have to open the card and edit it. However, knowing the date something was completed is important for reporting.
I am open to other suggestions!
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.4K Get Help
- 424 Global Discussions
- 221 Industry Talk
- 465 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 144 Just for fun
- 62 Community Job Board
- 463 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives