Sign in to join the conversation:
I'm trying to delete one task dependency on a Gantt chart. I found this quick YouTube video, which says to click the dependency line, but I'm unable to click on it. My dependency lines are not green like in the YouTube video. Thoughts?
Hello,
That YouTube video appears to be for a different piece of software other than Smartsheet.
If you're trying to delete a dependency in Smartsheet, delete the row reference that you see in the Predecessors column of the Grid portion of the sheet.
More information on dependencies in Smartsheet can be found in this help article: https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
How can you get rid of the uncategorized land in a report timeline view?
Please help! I understand that we can't customize the gantt chart bars anymore if it is a parent row but why am I getting random colors on the bar view in my report? I would prefer it remain grey. The first picture is the Smartsheet and the second one is the report pulling from the sheet.
Trying to understand why we don't have the option to remove a status by automation. For example, when external customer approves a proof, it fills in "APPROVED BY CUSTOMER" which then triggers automation, but the existing status of "SENT TO CUSTOMER FOR APPROVAL" remains as I cannot set automation to do that.