I'm trying to delete one task dependency on a Gantt chart. I found this quick YouTube video, which says to click the dependency line, but I'm unable to click on it. My dependency lines are not green like in the YouTube video. Thoughts?
Hello,
That YouTube video appears to be for a different piece of software other than Smartsheet.
If you're trying to delete a dependency in Smartsheet, delete the row reference that you see in the Predecessors column of the Grid portion of the sheet.
More information on dependencies in Smartsheet can be found in this help article: https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
The timeline widget seems to only allow filters to be set when you are editing the widget (see green highlight screenshot). Which is fine, but it would be more valuable to have regular users be able to adjust filters directly from the dashboard, similar to how there is an option to adjust the timescale. Am I missing…
Hello There , before smartsheet switched to the new license type, the users to whom I gave editing permissions could not share the page unless I granted them permission. In addition, users did not have the ability to create pages. This way, as the admin, I was aware of all the pages created in the company and could…
Can someone help me and give me an idea on how to create a cost estimate for installations, with a total for each chapter by groups, subgroups and types of work, but at the bottom of each chapter. https://us.v-cdn.net/6031209/uploads/0OSH46KSC2LH/cost-estimate.xlsx Thanks