I'm trying to delete one task dependency on a Gantt chart. I found this quick YouTube video, which says to click the dependency line, but I'm unable to click on it. My dependency lines are not green like in the YouTube video. Thoughts?
Hello,
That YouTube video appears to be for a different piece of software other than Smartsheet.
If you're trying to delete a dependency in Smartsheet, delete the row reference that you see in the Predecessors column of the Grid portion of the sheet.
More information on dependencies in Smartsheet can be found in this help article: https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
Is there a way to prevent a shared user from seeing the data in the "View Detail" option? I'm trying to make sure that when a user is given access to view a report, they can only view the columns present in that report. The view might only show certain columns but the user can then click on the record as shown below and…
I have a project sheet with a Gantt chart where the timescale headings are not aligning with my project’s fiscal year and start/end dates. Configuration: - Primary heading: Quarters (displaying as Q4 2026) - Secondary heading: Months (MMM format) - Fiscal year start: February 2 - Week start: Sunday - Project start date:…
Is there an overall calendar setting whereby I can choose a specific column to display in the calendar view? I have created an additional column that gives the task name (located in a child row) as well as the main task (in it's parent row). I want that to display in the calendar. Overall creating a content calendar and…