I'm trying to delete one task dependency on a Gantt chart. I found this quick YouTube video, which says to click the dependency line, but I'm unable to click on it. My dependency lines are not green like in the YouTube video. Thoughts?
Hello,
That YouTube video appears to be for a different piece of software other than Smartsheet.
If you're trying to delete a dependency in Smartsheet, delete the row reference that you see in the Predecessors column of the Grid portion of the sheet.
More information on dependencies in Smartsheet can be found in this help article: https://help.smartsheet.com/articles/765727-enabling-dependencies-using-predecessors
I am attempted to export to excel. I have two different smartsheet documents to export. One of them exported to excel fine, but not the other. This happened a few weeks ago. I make sure all columns were the correct size & no cells were hidden. "We have found a problem with (file) Do you want us to try and recover as much…
Hello Smartsheet Community, I need some help with a report that I created and shared with a customer. The customer is not seeing any of the information that is pulling into the report. See screen shot below that the customer texted me. I do have the report filter only showing the customer their product pulling from our…
BLUF: When I create an Invoice, I need the cell-link to my live price data to be severed. I currently have a Price sheet for my products that is updated frequently. I use Control Center to create Projects, which includes an Invoice sheet. I have a dropdown on my invoice sheet to select a product, and then I use Index…