Dynamic Durations
Minoguej
✭
I would like to calculate the duration based on two tasks. For example, I want a start date from say task 1 to be the start date of Task 2, while the end date of Task 2, to be the start day of task 100. The duration should of Task 2 will now be the total number of days between task 1 and task 100. If I adjust Task 1 or Task 100 then Task 2 duration should also update.
Any ideas?
Comments
-
Smartsheets doesn't let you create flex dates. Meaning, you can have a task start or end be based on a predecessor, not both. I've tried unsuccessfully to tie a start date to a predecessor and the finish date to another row. This is currently not possible at this time.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives