Dynamic Durations
Minoguej
✭
I would like to calculate the duration based on two tasks. For example, I want a start date from say task 1 to be the start date of Task 2, while the end date of Task 2, to be the start day of task 100. The duration should of Task 2 will now be the total number of days between task 1 and task 100. If I adjust Task 1 or Task 100 then Task 2 duration should also update.
Any ideas?
Comments
-
Smartsheets doesn't let you create flex dates. Meaning, you can have a task start or end be based on a predecessor, not both. I've tried unsuccessfully to tie a start date to a predecessor and the finish date to another row. This is currently not possible at this time.