Is this a bug? Why can I not get the parent level row to show day totals, for all of it's child rows?
Hello,
Duration in Smartsheet is the number of working calendar days it takes to complete a task. Parent rows don't total/sum the duration of all child rows, rather, they take the earliest start date and latest end date of all child tasks to roll up the duration.
I think you're expecting more of an effort calculation (number of work units in hours as totaled from all sub tasks), which it appears you may have already created in that Hours column to the right.
More information on parent roll up is available in the help center: https://help.smartsheet.com/articles/765753-parent-rollup-functionality
Hi All, I’m looking for some guidance on how to best structure an activity plan in Smartsheet. I need to track and display: Date ranges for each activity Activity month Monthly budget Key points such as promos/offers Major events happening during the same period (e.g., national holidays, International Women’s Day, etc.)…
I have given someone access as an Admin to allow them to create new sheets and edit existing and they keep being told they do not have access to edit. What could be causing this?
Hi everyone, hoping for a little help here, I recently did a survey of 240 employees with 9 yes or no questions. I am hoping to create either a linebar or stacked linebar graph showing the 9 questions in a single chart with the question being on the left axis. When I try to do a report to create this graph, Im unable to…