Is this a bug? Why can I not get the parent level row to show day totals, for all of it's child rows?
Hello,
Duration in Smartsheet is the number of working calendar days it takes to complete a task. Parent rows don't total/sum the duration of all child rows, rather, they take the earliest start date and latest end date of all child tasks to roll up the duration.
I think you're expecting more of an effort calculation (number of work units in hours as totaled from all sub tasks), which it appears you may have already created in that Hours column to the right.
More information on parent roll up is available in the help center: https://help.smartsheet.com/articles/765753-parent-rollup-functionality
Hi, I'm using smartsheet to track updates on each task in a tracker. These updates may span over a year, so they get lengthy. I was excited about smartsheets because viewing these notes is a lot cleaner. However, I've just realized that there is a content limit to a cell, which is a huge issue. While excel was annoying to…
Hello, i've a question about 2 tasks. Task 1 has for example 4 hours and should be on day 1 for example 6 january. Task 2 has 30 hours and should be on start on 4 january and futher. How can i manage that on 6 january task 2 has only 4 hours? Now i got the message user is over-allocated because task 2 is planned on a full…
Hi All, We have several update automations on various solutions - and have worked very well for getting info from people that dont have smartsheet access - how ever in Sept we switched over to SSO and MFA and activated the Safe Share - We have now run into an issue that when our update automations trigger and people within…