Is this a bug? Why can I not get the parent level row to show day totals, for all of it's child rows?
Hello,
Duration in Smartsheet is the number of working calendar days it takes to complete a task. Parent rows don't total/sum the duration of all child rows, rather, they take the earliest start date and latest end date of all child tasks to roll up the duration.
I think you're expecting more of an effort calculation (number of work units in hours as totaled from all sub tasks), which it appears you may have already created in that Hours column to the right.
More information on parent roll up is available in the help center: https://help.smartsheet.com/articles/765753-parent-rollup-functionality
@Paul Newcome , Hope you are well. Question for you, meant to ask quite some time ago but forgot. You had shared this right after Engage 2025. I'm unfamiliar with the view and how to create it. Can you tell me about this view?
I am trying to change owner on a Smartsheet sheet to the owner of the workspace it is located in. I keep getting an error message stating the permissions need to be managed at the workspace level. I am unable to change owner for the sheet at the workspace level. Not sure how to accomplish this change. HELP!
I would like to add two dynamic filters as a widget within my Dashboard to define a date range (start and end date) which would then return a count value to that same Dashboard. I have been searching for answers but am not coming up with the solution I'm looking for. What is the cleanest way to configure this?