Could the SmartSheet community get an update on the successor column from the products team? I believe this was first requested a few years ago in late 2015 and has been by others multiple times since then.
Thanks,
Riley
Hi Riley,
There currently isn't successors functionality in Smartsheet; only predecessors can be defined at this time. When you have a moment, please submit a product enhancement request using the form under Quick links to the right of the community site to make our Product team more aware of the popularity of this type of feature.
Is it possible to display both the planned and actual duration for a single task on a Smartsheet Gantt chart? I would like the Gantt bar to show the planned duration (e.g., in blue) based on a Planned End Date column, and then show the actual duration (e.g., in green) based on an Actual End Date column. Can the Gantt view…
I noticed in the Board View tags are grey by default but in the how to videos, in the Board View some of the tags are colorful. I'd like to leverage that same functionality as I'm building a research repository with many different types of research in it and a visual cue would be lovely. Can anyone assist? I attached a…
We want to know if it is possible to send request for update in one email, but with multiple rows at the same time. For example, staff A has 4 open referrals, I want to send one request for update automatically to them where they will receive only one email without having to overload them daily with all the open referrals…