Hi,
The scheduling tracking feature in Smartsheet shows that Parent Task is ahead of schedule for below, with Today = 10-Sep-2018
Task From To Completion
Parent 06-Aug-2018 21-Sep-2018 83%
Task A 06-Aug-2018 10-Aug-2018 100%
Task B 13-Aug-2018 17-Aug-2018 100%
Task C 20-Aug-2018 24-Aug-2018 100%
Task D 27-Aug-2018 31-Aug-2018 100%
Task E 03-Sep-2018 07-Sep-2018 100%
Task F 17-Sep-2018 21-Sep-2018 0%
Completion percentage from Task A to Task F are input by user while Completion percentage of Parent is auto-calculated. And, Task F is scheduled in next week.
From my user's perspective, the project is ON SCHEDULE while the tracking of bar chart in gantt is AHEAD SCHEDULE. See attached screen shot.
I think this is because the definition is different from each other.
In order to track the schedule from user's perspective, I have created the following two fields:
- Expected completed percentage; and
- SPI
with calculations below:
Expected completion Percentage
=IF([Planned Start]> TODAY(), 0, IF([Planned End] < TODAY(), 1, NETWORKDAYS([Planned Start], TODAY()) / NETWORKDAYS([Planned Start], [Planned End])))
SPI
=IF([Expected Completion (%)] <> 0, [Actual Completion (%)] / [Expected Completion (%)])
Eventually, the SPI calculated is exactly the same as what Smartsheet shows on gantt.
Question:
How to set the calculation if I want the result same as my user's expectation?
Thanks and regards
Frank