Show % progress on bars in Gannt view
Been searching and can not find any clear answer to this so ill ask (maybe again).
Is there a way of presenting the % progress within the bar of a task in Gannt view as it is as default in MS Project for example?
It could be enough to have it in 25,50,75,100% increments for me
Comments
-
Hi Mattias,
Yes, there is. In the Project Setting > Timeline Display > Display label for you can select which columns cell you want to show.
Pro tip: You can create a new helper column and combine (most of) multiple other values to show it on the Gantt bars.
I hope this helps you!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
That setting was just what I was looking for!
I'll get back to the pro tip when this current project is done...
-
Great!
Sounds like a plan!
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
This was very Helpful for my as well....How can I mirror those % of progress over to a Report.....When ever I Do I Always show a Full bar with out any progress mark....I Select the Start/End/Duration Column but nothing seems to work....
-
Hi @Karif
After you've added the % Completed column to the Report, you'll need to also configure the Project Settings within the Report to recognize this as the column to use for this specific Gantt view:
If you get a pop-up error when accessing your Project Settings in a Report, there is a current issue happening where this error message can occur based on your organization's settings. To resolve this in the interim while we work on a fix, have your System Admin toggle off "10,000ft Resource Management" (see the steps for this here).
Cheers!
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.8K Get Help
- 406 Global Discussions
- 218 Industry Talk
- 457 Announcements
- 4.7K Ideas & Feature Requests
- 141 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 297 Events
- 37 Webinars
- 7.3K Forum Archives