There is an Task hierarchy created with the layer of 5 Main sub task.
For this 5 layer Sub task Duration calculation is wrong when i tried with dependency and without dependency
Can any one help me on this
Hi Sara,
It looks and probably is correct. Check your Project Settings > Working Days so that is set up the way that you want.
The Start Date for a Parent will be automatically set to the earliest Start Date from all of its Child Rows. Similarly the End Date will be set to the last End Date from all its Child Rows.
The Duration on the Parent reflects the number of working days between the Start Date and End Date in that row. It provides the full time span encompassed by that section of tasks, from the earliest sub-task to the latest, as opposed to a sum of their durations.
The % Complete on the Parent row will calculate a weighted percentage based on both the Duration and % Complete entered on each child row. In this way, completing child rows with shorter durations won’t affect the Parent row % Complete as much as completing a longer duration child row. Because of the way this is calculated, only sub-tasks with a given Duration and a given % Complete value will be included in the parent row roll-up.
More info: https://help.smartsheet.com/articles/765753-parent-rollup-functionality
I hope this helps you!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
I have an employee with an Android phone. He has just downloaded the Smartsheet app and cannot view sheets in landscape orientation. I have an iPhone, so I'm not much help. He tried changing his settings to "auto-rotate" but that did not work. Any ideas/solutions? Thanks!
This discussion was created from comments split from: Attachment/sheet size maximum limit.
Hi, I did a backup of all my workspaces before my license expiry and got confirmation mail for the backups. I still have access to Smartsheet, but I don't see the backups done as I would like to download them. Can someone guide me on how to download the backups please?