Sign in to join the conversation:
There is an Task hierarchy created with the layer of 5 Main sub task.
For this 5 layer Sub task Duration calculation is wrong when i tried with dependency and without dependency
Can any one help me on this
Hi Sara,
It looks and probably is correct. Check your Project Settings > Working Days so that is set up the way that you want.
The Start Date for a Parent will be automatically set to the earliest Start Date from all of its Child Rows. Similarly the End Date will be set to the last End Date from all its Child Rows.
The Duration on the Parent reflects the number of working days between the Start Date and End Date in that row. It provides the full time span encompassed by that section of tasks, from the earliest sub-task to the latest, as opposed to a sum of their durations.
The % Complete on the Parent row will calculate a weighted percentage based on both the Duration and % Complete entered on each child row. In this way, completing child rows with shorter durations won’t affect the Parent row % Complete as much as completing a longer duration child row. Because of the way this is calculated, only sub-tasks with a given Duration and a given % Complete value will be included in the parent row roll-up.
More info: https://help.smartsheet.com/articles/765753-parent-rollup-functionality
I hope this helps you!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
We changed from an enterprise licence to specific accounts. I have a licence and setup a workspace for our global team to edit and collaborate across various sheets. I granted editor can share rights to all non licensed members and shared the publish link with them. This has worked well and allowed them to edit cells,…
This is pulled from a column of responsible person. Why does it display email and not name. How do I correct?
Hi! I have a sheet that has two form that feed into it. This is to report on Closures due to Staffing, Weather, and Facilities. One team submits closures for Staffing and Weather, while another team only submits Facilities. When I created this set up I have it so the one team gets asked "Reason?" then they can select…