entering dates
Comments
-
Could be a couple of things:
- If you have tasks indented below - it will disappear (but generally tell you with a pop-up) that it is dependent on sub-tasks
- If you have dependencies - you might have set the date before the prior activity date
- Sometimes having a start date, end date and #days can affect this. You have to do this in the right order if you are changing something previously populated
-
This is likely due to predecessors. Try removing all the predecessor values then change the dates.
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives