I have an estimated project Finish date of 8/9/16 in a column "Finish". this date is in row 6 and row 161. I have entered a row name TODAY and set the date to current date in the 'Finish" column row 4.
I attempted to use the formula:
=NETDAYS([Finish]6,[Finish]4)
I get no result or error message. Just the formula.
What am I doing wrong?