Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Non-Working Day Exceptions
Comments
-
Joe,
Sort of.
You can't have a task that starts earlier and carries over that particular Saturday (or Sunday), but you can allocate resources on that particular day.
You just need to add a 1 day (or less) task that starts and ends on the non-working day in questions. This also goes for "gotta work the weekend" tasks -- where you will need two 1 day tasks to allocate them properly.
Hope that helps.
Craig
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.1K Get Help
- 414 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives