Non-Working Day Exceptions
Comments
-
Joe,
Sort of.
You can't have a task that starts earlier and carries over that particular Saturday (or Sunday), but you can allocate resources on that particular day.
You just need to add a 1 day (or less) task that starts and ends on the non-working day in questions. This also goes for "gotta work the weekend" tasks -- where you will need two 1 day tasks to allocate them properly.
Hope that helps.
Craig
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.4K Get Help
- 394 Global Discussions
- 213 Industry Talk
- 449 Announcements
- 4.6K Ideas & Feature Requests
- 141 Brandfolder
- 132 Just for fun
- 131 Community Job Board
- 453 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 293 Events
- 35 Webinars
- 7.3K Forum Archives