Hi,
I am new to Smartsheet. I have a project that has multiple tasks and dependencies. If I have a task that is completed ahead of time and I mark the '% Complete' to 100%, I would like the dependent tasks to update. (I have the Dependency Settings enabled in Project Settings) For example if a task is due to finish on 6th April but it finishes 25th March, for the tasks that would have then started on 7th April - how do I get them to automatically change the start date to 26th March?
Thanks in advance,
Richard