Modifying resource views
Good day and thanks in advance!
Doing as I understand it's supposed to, when i open a resource view and select (and expand) a resource, all sheets with that resource are there and roll up to the total resource allocation for that resource.
My challenge is that I have multiple earlier versions of plans I've developed, with resources identified that I save for later reference. This becomes a problem in that the total resource allocation is not correct.
Is there a way to deselect the sheets included in the view that are not "active"?
Thanks again,
Richard
Comments
-
Hi Richard,
Yes, there are. In the Resource View > Edit (right upper corner) > Select/deselect as needed.
Hope that helps!
Have a fantastic weekend!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
Thanks Andree
-
Happy to help!
Best,
Andrée
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 136 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives