Sign in to join the conversation:
When export my Project to Microsoft Project, start and due dates doesnt Match with smartsheet dates. Some one know that do I need yo do to hace the same information?
I had the same issue a client was facing and it was quicker to start from scratch. There are a lot of posts in here from others re. MSP - check that out first, but, Smartsheet doesn't support a 1-for-1 import.
Sean
Hi everyone, I have a Smartsheet that has requests for updates that go to 10 different departments. We are asking that each step in the process be completed within 24 hours. I would like to track the time it takes to complete each step. Here's the complication, there are requests that go out to say 3 different departments…
Does anyone know how to generate a chart like the one in the picture in Smartsheet? We want to show planned hours vs worked hours by month by team. Thanks!
I have a simple "copy row" automation that is delaying execution. Most recently, it delayed 16 hours - it was supposed to complete one afternoon, but did not until the following morning. It is working out of a very busy project tracker, so I assume there are too many workflows happening at the same time. How am I able to…