When export my Project to Microsoft Project, start and due dates doesnt Match with smartsheet dates. Some one know that do I need yo do to hace the same information?
I had the same issue a client was facing and it was quicker to start from scratch. There are a lot of posts in here from others re. MSP - check that out first, but, Smartsheet doesn't support a 1-for-1 import.
Sean
Hi everyone, My boss is bringing data in from my Smartsheets into PBI. He is having issues with the dollar value columns showing up as text instead of dollars. There is no option for the column except for text/number. What can I do to solve this problem? Thanks! Freda
I have a project tracking sheet that is updated weekly with the most recent updates for project progress, issues/concerns, barriers requiring intervention and next steps. How can I display only the most recent updates for these 4 columns in a dashboard?
How do I make a dashboard available so that anyone can access it without having to login?