Mark which task is the deadline?

Jennifer Levey
edited 12/09/19 in Smartsheet Basics

I have a set of tasks in a schedule to prepare for a software release - which is the ultimate goal and deadline we are working towards. I want to see the critical path for this release.

But, I also have some tasks in the schedule of things that need to be done after the release, and Smartsheet is showing me the critical path for those tasks. Is there a way to keep all the tasks in the same schedule, but tell Smartsheet which task I want to see the critical path for?