Mark which task is the deadline?
I have a set of tasks in a schedule to prepare for a software release - which is the ultimate goal and deadline we are working towards. I want to see the critical path for this release.
But, I also have some tasks in the schedule of things that need to be done after the release, and Smartsheet is showing me the critical path for those tasks. Is there a way to keep all the tasks in the same schedule, but tell Smartsheet which task I want to see the critical path for?
Comments
-
Hi Jennifer,
This might help: https://help.smartsheet.com/learning-track/smartsheet-advanced/critical-summary-and-driving-paths
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
-
I was thinking driving path (part of Andree's link).
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 66.1K Get Help
- 430 Global Discussions
- 149 Industry Talk
- 490 Announcements
- 5.2K Ideas & Feature Requests
- 85 Brandfolder
- 154 Just for fun
- 74 Community Job Board
- 499 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 305 Events
- 36 Webinars
- 7.3K Forum Archives