I want to denote unavailable time for resources so when a task assigned to that person fell on an unavailable time period, the start and end dates accomodated for that automatically. Is there a way to do that in smartsheet?
Not with dependencies enabled. With dependencies not enabled, you would need a few helper columns to essentially replace the dependencies function and to work in the vacation scheduled.
This discussion was created from comments split from: Plan Asset Manager - will it capture orphaned assets already in the system?.
In the new USM, are users who are designated as Viewers only able to download/export sheets they are given access to e.g. to Excel?
I just tried to create my first dashboard using the timeline chart widget. I have set it to open the source data when clicked however it does not work. I've done this multiple times without success. It seems this is not actually an option even though you can select it in the settings. Can someone verify this or is thereā¦