Limiting the dates that print in Smartsheet
I want to create a Smartsheet project that has a Start Date of July 1, 2019 and End Date of September 1, 2020. I want to set the timeline to Years/months. When I view or print it, I only want to see the months associated with 2019 and 2020 and I don't want to see any months in 2021. How do I do this? I can't hide the columns in the date section because they are locked.
Thank you,
Comments
-
Hi,
In the Project Settings > Timeline Display, you can select Primary heading (Years) and Secondary heading (Months) and then when you print, you can select a Custom Date Range.
Unfortunately, it's not possible at the moment to make the same settings for viewing the sheet, but it's a great idea!
Please submit an Enhancement Request when you have a moment.
Hope that helps!
Have a fantastic week!
Best,
Andrée Starå
Workflow Consultant @ Get Done Consulting
SMARTSHEET EXPERT CONSULTANT & PARTNER
Andrée Starå | Workflow Consultant / CEO @ WORK BOLD
W: www.workbold.com | E:andree@workbold.com | P: +46 (0) - 72 - 510 99 35
Feel free to contact me for help with Smartsheet, integrations, general workflow advice, or anything else.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives