Project Template Move Start Dates
Colin Whelan
✭✭
I have a project template that has a requirement to have a start date set of which I choose and I dont see a way of 'moving' the whole project to a new date, is this possible?
Comments
-
Colin,
I typically have a "Permission to Start" task at the beginning of a project.
The tasks that can start immediately have that task as a predecessor.
The whole project is under a single parent, so if I change Permission to Start's start date to something in the future, the entire project should shift - and I can see this by looking at the parent rollup dates.
If it doesn't, then there is a some tasks that do not have predecessors.
I hope that helps.
Craig
-
thanks for the info Craig.
This discussion has been closed.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.7K Get Help
- 433 Global Discussions
- 136 Industry Talk
- 468 Announcements
- 4.9K Ideas & Feature Requests
- 143 Brandfolder
- 147 Just for fun
- 64 Community Job Board
- 466 Show & Tell
- 32 Member Spotlight
- 2 SmartStories
- 298 Events
- 36 Webinars
- 7.3K Forum Archives