Project Template Move Start Dates

Colin Whelan
Colin Whelan ✭✭
edited 12/09/19 in Archived 2016 Posts

I have a project template that has a requirement to have a start date set of which I choose and I dont see a way of 'moving' the whole project to a new date, is this possible?

Comments

  • J. Craig Williams
    J. Craig Williams ✭✭✭✭✭✭

    Colin,

     

    I typically have a "Permission to Start" task at the beginning of a project.

    The tasks that can start immediately have that task as a predecessor.

     

    The whole project is under a single parent, so if I change Permission to Start's start date to something in the future, the entire project should shift - and I can see this by looking at the parent rollup dates.

    If it doesn't, then there is a some tasks that do not have predecessors.

     

    I hope that helps.

     

    Craig 

     