Welcome to the Smartsheet Forum Archives


The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.

Linked Cells and Indentation

Mark Kennedy
edited 12/09/19 in Archived 2016 Posts

I'm pretty new to Smartsheet so please forgive any ignorance I may have.  

 

I have a program with three providers managing their portion of the program.  I want to have each provider maintain their own schedule in their own sheet and have a master sheet that includes all the tasks that I'm managing as well as links to all the tasks in their plans.  That way, we all control our own schedules and don't have to work out of the same sheet. 

 

However, when I use cell linking to include tasks from the other sheets (task name, start, finish, etc.), I lose the indentation associated with the Task Name column. Obviously, this makes it very difficult to see the hierarchy of the tasks from the other sheets. 

 

Is there any way to accomplish this?

 

Thanks much for any feedback you can provide. 

Comments

  • J. Craig Williams
    J. Craig Williams ✭✭✭✭✭✭

    Mark,

     

    Are the providers adding tasks to their portion or only updating the existing tasks/rows?

     

    Craig

     

     

  • Craig,

    They may be adding tasks as the project goes along.

     

    Thanks,

    Mark

  • J. Craig Williams
    J. Craig Williams ✭✭✭✭✭✭
    edited 06/19/16

    Mark,

     

    That rules out a single sheet with the providers doing their updates from individual Reports. (They still would need to be shared to the underlying sheet, but normal ops would be via the Report)

     

    Adding links will be a pain and you will likely run into the limit (500 incoming links, IRCC)

     

    You could try building a report to bring the four sheets together (3 providers' and yours). This will also lose the hierarchy.

     

    I'm afraid you might be out of luck here.

     

    What I have done in the past is have a Master schedule that showed the overview (major milestones and tasks). These flowed DOWN (via links) to the another more detailed schedules (by engineer or team) where the WBS was broken down into the activity lists. The activities were linked back up to the Master schedule so that when things started to shift to the right, the Master schedule would show the slippage.

    I don't currently have an example but it was fairly simple to set up and most of the maintenance was done by the task holders. I'm not sure that will help, but I figured it won't hurt to mention it.

     

    Craig 

     

     

     

  • Mark Kennedy
    edited 06/19/16

    Craig

    thanks for the feedback.  That's kind of where I was heading in my thinking.  Thanks a lot for your insight. 

     

    Mark

  • J. Craig Williams
    J. Craig Williams ✭✭✭✭✭✭

    Always glad to help.


    Craig

  • Hi Craig,

    I am new to Smartsheet but am trying to handle exactly the same issue as was mentioned by Mark. Would there be any video that could help show me exactly what do to.

    Many thanks for in advance.

    Kind regards,

    Taru

This discussion has been closed.