Hi struggling a bit on the correct formula for overdue tasks
Hi,
I need a function to look at If a column completed date is blank and the end date column date i s more than today to the return status "overdue" so I can report on overdue tasks ?
Comments
-
this works
=IF(ISDATE([completed date]1), "", IF(TODAY() > [end date]1, "overdue", ""))
this one checks to make sure end date has a value
=IF(ISDATE([completed date]1), "", IF(TODAY() > [end date]1, IF(ISDATE([end date]1), "overdue", ""), ""))
-
Great thanks Tracy,
That works a treat just what I needed
-
James: Will other folks access this overdue information via reports, or will your overdue tasks be noted only within the sheet?
-
Yes a Report will flag the overdue information accesable by others as well
-
James: Cool. Then, I have another question for you. I've got a similar set-up. I've noticed, however, that the formulas do not update, unless you open up the sheet. This isn't an issue normally, if you are in that sheet every day. However, if you are out of the office for a while and nobody opens the main sheet, then the overdue calculations are not updated on the reports. Please let me know if you see this too.
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 437 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives