Nested If with Multiple Conditions Automation for Project Management
Hi SS Community!
Had a complicated question and my formula keeps coming back unparseable, so I wanted to run this by you and see if anybody could help me.
Currently, I have this:
=IF(AND([Start Date]@row < (TODAY() + 14)), NOT(OR([Status]@row)="Complete"), ([Status]@row)= "In Progress"),"On Deck", "Not Started")
I just need to automate
If the start date is within 2 weeks and the status is not complete or in progress, then mark it as on deck.
Otherwise, default to not started.
Thanks for the advice in advance!
Comments
-
You prematurely closed off your or statement and didn't close the not afterwards
=IF(AND([Start Date]@row < (TODAY() + 14)), NOT(OR([Status]@row="Complete", [Status]@row= "In Progress")),"On Deck", "Not Started")
-
=IF(AND([Start Date]@row < (TODAY() + 14), NOT(OR([Status]@row="Complete", [Status]@row= "In Progress"))),"On Deck", "Not Started")
You also prematurely closed your and statement. Missed that in the first answer.
-
Hmm, it says that it's a circular reference. Any way that I can fix this? I am putting this in the column titled "Status".
Thank you!
-
You can't reference the current cell for a value, then change that value. I think your best solution is to add another column to have this work properly.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 437 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!