Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Calculate % complete based upon start and end dates?
Hello, does anyone know how to calcuate the % complete for a project based upon it start and end date? I have projects where my resources are "consulting" and I'd like to have a way to see the % complete of the project when I roll it up in a project overview dashboard.
I tried using the traditional "yearfrac" formula utilized in Excel but this doesnt appear to be supported.
Thanks for your help!
Mike
Comments
-
Hi Mike—one important note on this is that if you have dependencies enabled in your sheet, there isn't currently a way to place custom formulas in the % complete column as it's being used to calculate the weighted parent roll up functionality.
If you don't have dependencies enabled in your sheet, you'll need to create a custom formula that calculates the percentage for you in a manner that you see fit. Although we don't have a YEARFRAC function in Smartsheet, I'd recommend checking out our Help Center to see what you can come up with: http://help.smartsheet.com/articles/775363-using-formulas
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 414 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives