How to display: "A must be done before B starts, but B doesn't start immediately after A"

Hello community,

I would like to use the following dependency in a project plan:

"A must be done before B starts, but B doesn't start immediately after A".

There is a predecessor relationship between A and B, so that B can be defined as the predecessor for A. The standard at Smartsheet now works in such a way that the starting time for the following work package B begins directly after A. However, B has a starting time that does not directly follow A, but e.g. at a defined point in time X. This point in time X is also not to be numbered „exactly 2 weeks after A", but simply a point in time X.

Can this relationship be illustrated in Smartsheet? If I try to enter these (expected) fixed values, I will lose the previous relationship, which should still exist.


Best regards and many thanks,

Jonas

Answers