Welcome to the Smartsheet Forum Archives
The posts in this forum are no longer monitored for accuracy and their content may no longer be current. If there's a discussion here that interests you and you'd like to find (or create) a more current version, please Visit the Current Forums.
Change Status Bubble Color Based on Percentage
Have tried using conditional formatting to achieve this with no luck. I have a column of % complete with percentages in increments of 5. I then have a seperate column of status that I am using a gray, red, yellow and green ball image. I'd like to for the color of the ball to change based on the percentage chosen (i.e. gray =0, green = 100, red = 5 to 50, yellow = 55 to 95). Any ideas?
Comments
-
You can do it like this...
https://app.smartsheet.com/b/publish?EQBCT=0383f2e8ef4b455990bca7cecc8526b9
The formulas are at the bottom,
-
Thanks. Wasn't sure if formulas would work, but now that I know they do, I can work on getting that part done, plus some other items that require similar programming.
-
I found that if I want to use whole numbers in the % column (25%, 50%, etc.), the formula should use decimals since that's how it will translate, once the % column is formatted.
e.g. (IF %Complete2 < .25, "Green")
-
Is there a way to use this same concept with Not Started, In Progress and Complete instead of the colors?
-
Yes,
something like this
= if ( status-as-text-column&row = "Not Started", not-started-color,
if ( status-as-text-column&row = "In Progess", in-progress-color,
if ( status-as-text-column&row = "Complete", complete-color, "I did not find a match")
Craig
-
can you add link to the Due date so that if due date is in next X days and % <> 100% then RED
currently have this:
=IF([% Complete]3 = 0, "Gray", IF(AND([% Complete]3 > 0, [% Complete]3 < .51), "Red", IF(AND([% Complete]3 > .50, [% Complete]3 < .96), "Yellow", IF([% Complete]3 = 1, "Green"))))
-
Patrick,
Here's my take on it:
=IF([% Complete]3 = 0, "Gray", IF([% Complete]3 = 1, "Green", IF(OR(AND([Due Date]3 < TODAY() + 5, [% Complete]3 < 1), [% Complete]3 <= 0.50), "Red", IF([% Complete]3 < 1, "Yellow"))))
I changed a few things:
1. These AND's are not needed
AND([% Complete]3 > 0, [% Complete]3 < .51)
if the IF's are nested properly. The first IF checked for =0. Unless you are concerned about negative percentages, the >0 is not needed.
Same with the next one in your original formula.
2. I changed < 0.51 to <= 0.5
In your formula, you would have shown Red at 50.5%, which I don't think you wanted.
3. I changed the order to check for Gray, then Green, then Red, and finally Yellow.
In this case, mostly a matter of preference. See also below on missing date.
4. I changed Yellow to less than 100%
In your original formula, 96.1% to 99.9% (rounded) did not get a result.
One thing neither of our formulas account for is a missing date (non-started and complete will be correct (see #3)) but otherwise Red. That's probably OK.
Hope this helps.
Craig
-
Hi
This is very usefukl for one project I wanted to report on so a huge thanks for that.
Where I think this needs a tweak is around the colours.
Gray = No started (Good for me)
Green = Completed (Good for me)
I need Yellow to indicate that this is progress
I need Red to indicate that either it's not started or less than 75%and the due Date is in xx days
I need Red to indicate % Complete < 1 and Due Date = < today()
Does that make sense...? Or how else do people track these things?
-
That is awesome - thank you so so much for assisting with this. would have taken me hours....!! Seem to work a treat.
-
It does.
I had a longer post, but a blue screen of death wiped it.
Here's the updated formula, rearranged again.
I added blank dates check for Gray result.
I'm using 5 as the X days. It shows up in two places
=IF([% Complete]6 = 1, "Green", IF(AND([% Complete]6 = 0, OR([Due Date]6 > TODAY() + 5, ISBLANK([Due Date]6))), "Gray", IF(OR([Due Date]6 > TODAY() + 5, AND([Due Date]6 > TODAY(), [% Complete]6 > 0.75)), "Yellow", "Red")))
Here's a picture of the results:
Hope that helps.
Craig
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives