This may sound like a foolish questions..... I specify my task durations in days. Can I specify some of them in months? The reason I ask is that I noticed that when I enter a duration as 6 it displays "6d" for 6 days. We have a number of tasks that have contractual commitment in 3 months. Therefore, the need to be able to specify in terms of months.
Comments
-
Jerry,
The closest you have is either 4w (4 weeks) or more accurate most of the time would be e91d for 3 months.
The "e" tells it to ignore non-working days so this is 91 calendar days (pretty close to 3 months)
Note that 91d without the "e" is work-days so 18+1 work-weeks, not 13 for a quarter.
Contrarily, "4w" is only 20 working days (for a 5 day work week) and is not equal to 28d
Hope this helps.
Craig
-
Thanks, Craig! I will look at this more closely. It sounds like a good possibility.
Thanks, again...
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 441 Global Discussions
- 139 Industry Talk
- 472 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 68 Community Job Board
- 496 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives