Time controlling
We planed a rough schedule for our project. Now we need to plan new, because of the changes in the project. Also we want overlay the old plan with a new one so we ca see consequences.
So I could see it is possible to add new columns and chose datatype for them. Unfortunately new bars are not shown.
Why is it so? What can I do to solve this problem?
Thank you
Best Answer
-
Save as New your Project Sheet. Then update the dates in the new copy. Create a report that references both the original and the copy, and then you should see the old vs the new together.
Answers
-
Save as New your Project Sheet. Then update the dates in the new copy. Create a report that references both the original and the copy, and then you should see the old vs the new together.
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.3K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 142 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives