My parent rollup is not working properly
I am new, so feel free to correct me if it appears I am not understanding:
My parent row should show the earliest start date from the values in the child rows, but it is blank. And it is editable.
I have decreased the indent, saved, increased the indent and saved, but it is still not working.
Please advise - and thank you in advance.
DLutz
Answers
-
Hi @Dreama Lutz
Is it possible to share a screenshot or a mocked up spreadsheet, along with the formula that you are using? If not obvious, please indicate which column your formula is in. Please remove any sensitive data.
-
Thank you @KDM - I discovered the issue is being caused by the Dependency Settings in the Project Settings window. We have Target Start / End dates for planning with Actual Start / End dates for once the project goes live. This activity has an AS date, but the program is looking at the Target Dates for dependencies.
I am hoping that this will resolve itself once the PMs have made the adjustments and we go live. At that point I will reassign the dependencies.
Thank you for taking the time to try to help a newbie!
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 62.9K Get Help
- 376 Global Discussions
- 207 Industry Talk
- 440 Announcements
- 4.5K Ideas & Feature Requests
- 139 Brandfolder
- 129 Just for fun
- 130 Community Job Board
- 449 Show & Tell
- 30 Member Spotlight
- 1 SmartStories
- 284 Events
- 33 Webinars
- 7.3K Forum Archives