Project sheet - Date not working

jb@59069
jb@59069 ✭✭✭✭✭✭
edited 01/27/21 in Smartsheet Basics

All of our Project sheets have stopped accepting dates in the Start Date and End Date columns.

These are sheets from the "Template Set - Project Tracking and Rollup"

No matter who attempts to enter a date, me (the Owner), an Admin or Editor, the exact same thing happens:

Either select a date from the drop down or manually enter a date, it flashes then the cell goes blank.

  • columns are configured correctly as "Date" columns
  • Project Settings are configured correctly

PLEASE HELP!

Answers

  • Hi @jb@59069,

    I can see that you worked with our Support team on this and that you were able to resolve the issue by unhiding your Predecessors column and removing parent-row predecessor values. Glad to hear you're now able to enter dates into the Start and End date columns in your sheet!

    Thanks,

    Ben