Automatic calculation of lag time
Hello Smartsheet community!!
I hope someone can help me with the following question:
I have 1 activity that depends on another BUT does not necesarly needs to start right after the predecent activity finish. I know that the duration of the activity is 2 days, and the exact date when it has to be finish. Is there any way to set dependency and the end time so Smartsheet automatically calculate the lag "days" ?
Hmm difficult to explain so tons of thanks for any help.
KR,
Anna
Comments
-
Anna,
If I understand correctly, you have two conflicting constraints.
1. Task C can start after Task A is completed.
2. Task C must finish before a deadline (let's call that Task
You first option is to see Task C's predecessor to Task B as a Finish-to-Finish relationship.
This means that Task C can't finish before Task B finishes.
With a 2 day duration, this will show up with a [Start Date] of 2 days before the deadline.
Then set a Conditional Notification on Task A to send an email to the person responsible for Task C when Task A is finished - letting them know they can start.
Craig
-
Hello Craig and thanks a lot for your comment.
I think I will rephrase my question so it's easier to understand.
My question is only about 2 tasks, I liked the way you formulated your answer so lets keep calling them A and B.
Example:
1. Task A finishes the 31st of Jan and tasks B depends on tasks A but I want it to start on May 25th.
2. I know that tasks B only takes 2 days to perform.
The only way for me to ensure that the Gantt Chart is correct with dependencies between A and B is adding the correct lag days between the 31st of January and May (this I have to count manually).
Smartsheet only allows me to write the exact number of days between this 2 dates. Is there any way for me to only choose the exact date when I would like task B to start? or do you have any other way to do this?
I hope my questions i more clear now
Kind Regards,
Anna
-
Anna,
In my opinion, you have TWO constraints on Task B.
1. Task A completed.
2. Start no earlier than May 25th.
In some other PM tools, you can set both of those in the constraints for Task B.
Not in Smartsheet.
The way I get around this is to add another task (C) with 0 duration and start/end dates of May 25th.
Task B then points to Task A and Task C.
If Task A goes past May 25th and the schedule is updated to reflect it, Task B's start date shifts.
(Note that Task A/B/C no longer match my other post)
Craig
-
Interesting workaround. I will try it for sure!
Thanks a lot Craig for your good advise always really appreciated.
Have a lovely day,
Anna
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 63.9K Get Help
- 410 Global Discussions
- 220 Industry Talk
- 458 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 137 Just for fun
- 57 Community Job Board
- 459 Show & Tell
- 31 Member Spotlight
- 1 SmartStories
- 298 Events
- 37 Webinars
- 7.3K Forum Archives