Health of Task or Project using % Complete & Finish Date - Sanity Check
I found something close to what I am looking for here:
This formula doe s a great job of flagging the dates in relation to time left.
However, I am looking for a health check that can take into account both percentage complete and time left.
I am not sure I have gone about my solution the right way. I am making this post for the community to walk through what I have done as a sanity check or find potential gaps I have not accounted for. Thank you in advance for your review and input.
Phase 1: Initial Easy grab formulas
- If % Complete = 1, Up (This means we are done)
- If % Complete = 0 and if Today's Date >End Date, Down (This means we have not started and currently behind)
Phase 2: Helper columns
Now the next set of ideas and thinking is where I keep going in circles. I am not sure the best way to organize the data. I have three helper columns currently.
Helper Column 1 (HC1): % Progress
HC1 Reason: Manually entered in weekly/daily meetings
HC1 Formula: No formula just a fill in text/number cell
Helper Column 2 (HC2): % Delta
HC2 Reason:: This helps me calculate where Today I am in relation to the upcoming end date and puts out a percentage of time that has passed. My percentage is showing as a negative when it is a very large amount of days out from completion. So I have put an IF statement to zero it out and only start taking into account a percentage counter when the percentage is greater than zero.
HC2 Formula:
=IFERROR(IF((1 - (([End Date]@row - TODAY()) / Duration@row)) > 0, 1 - (([End Date]@row - TODAY()) / Duration@row), 0), "")
Phase 3: Logic Ranges
So I created a table in the order I would like to do a check so if you see a 1 2 3 or 4 in the FALSE portion of the statement. That is telling me where I should be copying my next formula.
You should also know that when I create long strings of statements I do them in individual cells to test the logic and then string them together in my final cell with formatting.
EXAMPLE of my Cells and Testing Logic:
Logic Check of what I am wanting:
0 - If my project is complete I'm done - Up Health
1 - If my timeline has started but I have not made any progress - Down Health
2 - If my completion is less than 80% and my time passed is greater than 90% - Down Health
3 - If my completion is less than 100% and my time has passed the delivery date - Down Health
4 - If at any time the difference of % Complete and % Delta is greater than 15% - Down Health
IFERROR was added with a "MILESTONE" tag for some durations that are going to net me a 0.
Final formula:
=IFERROR(IF([% Complete]@row >= 1, "Up", IF(AND([% Complete]@row <= 0, [% Delta]@row > 0), "Down", IF(AND([% Complete]@row < 0.8, [% Delta]@row >= 0.9), "Down", IF(AND([% Complete]@row < 1, [% Delta]@row > 1), "Down", IF(([% Delta]@row - [% Complete]@row) > 0.15, "Down", "Up"))))), "MILESTONE")
Formatting Properties:
If you have made it this far. Thanks for the read. Maybe this will be helpful to someone later on.
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.8K Get Help
- 434 Global Discussions
- 138 Industry Talk
- 470 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 65 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!