Actual vs target Date
Hi,
Need a help
if my Start Date is 05/24/2021 and end date is 07/01/2021
and in my project plan sheet say i have a task that start on 06/24/2021 and end on 06/28/2021 .However, that task is already been completed and the actual % Complete has been updated to 60% for that task i want the schedule Health should be turn to Green for that task.
can someone help me with a formula .
As now its changing to red.
=IF(Status@row = "In Progress", "Red", IF(Status@row = "Complete", "Green", IF(Status@row = "Not Started", "Gray", IF(Status@row = "On Hold", "Yellow", ""))))
Answers
-
Hi @Finops C'ship. I'm confused by the scenario. Can you share a screenshot of the row in question.
My confusion is in the value of 60%. If the status of the task is "Complete", shouldn't the % Complete be 100%? Also, based on the formula you referenced, the % complete has no impact.
So, my assumption based on what you've shared is that for some reason this completed task is still showing a task status of "In Progress".
For this reason, I think a screen capture will provide clarity and guide a resolution to your inquiry.
Thanks.
-Jen
-
Hope you are fine, Please add a copy of your sheet or a screenshot (after removing or replacing any sensitive information). This will make it easier for me to provide the appropriate answer to your question.
bassam.khalil2009@gmail.com
☑️ Are you satisfied with my answer to your question? Please help the Community by marking it as an ( Accepted Answer), and I will be grateful for your "Vote Up" or "Insightful"
Help Article Resources
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.2K Get Help
- 419 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 143 Just for fun
- 58 Community Job Board
- 463 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 300 Events
- 39 Webinars
- 7.3K Forum Archives
Check out the Formula Handbook template!