Hi,
I have a problem I am trying to solve in a sheet that contains hundreds of individual requests. Each request starts with Status = 'New' and finishes at Status = "Complete" in between there are 3 review statuses, "Review Department A", "Review Department B", "Review Department C" depending on the department the review is with. These review statuses move back and forth until all issues have been resolved with the request
How would I calculate the total duration in days of the time spent in each status?
A status history for one request on this sheet looks like this
I cant use the dates applied in the Cell History with formulas/automation, and I don't think the record date automation will help as this will overwrite the previous date recorded for each status.
Thanks,
Ross