One Project - Multiple Clients
I have one project where certain tasks are paid by one client and the remaining paid by a another.
Example: Data collection paid by Client A, Data Cleaning paid by Client B
How would I set this up so when the smartsheet project is linked to resource managment the allocations are assigned to the correct client /budgets?
Answers
-
Hi @EVLevett
In order for your Clients to be automatically assigned to your tasks in Resource Management via the Resource Management Panel, you'll want to ensure "Client A" and "Client B" are each either a valid managed user or Resource Management placeholder in the Assigned To column.
To be a managed user, they would need to have an email address associated with your company's plan (ex. an unlicensed Member in your Smartsheet plan).
There's a webinar on Resource Management here, if that helps!
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Smartsheet Customer Resources
- 64.1K Get Help
- 414 Global Discussions
- 221 Industry Talk
- 461 Announcements
- 4.8K Ideas & Feature Requests
- 143 Brandfolder
- 141 Just for fun
- 58 Community Job Board
- 462 Show & Tell
- 32 Member Spotlight
- 1 SmartStories
- 299 Events
- 38 Webinars
- 7.3K Forum Archives