Resource Management: Can we allocate a weekly time for internal meetings on a regular basis?
Hello,
I am setting up resourcing for a team to an internal weekly meeting. Is there a way to allocate a weekly time for internal meetings or regular scheduled meeting/activities within resource management?
I only seem to be able to have the team manually add in this time or, have an allocation for a certain % for every single team member.
Is there a way around this?
Thanks in advance for any help or advice on whether this is possible.
Claire
Answers
-
Hi @Claire A
Yes this is possible!
The way I would do this is to create a meetings Project, then set a Task and add the team members you want to attend the meeting.
Once you have a person added, then you can set the Allocation for that person as the duration of the meeting (for example, 1 or 2 hours).
Then you can repeat this assignment every week. See: Repeat Assignments for more information.
Cheers,
Genevieve
Need more help? 👀 | Help and Learning Center
こんにちは (Konnichiwa), Hallo, Hola, Bonjour, Olá, Ciao! 👋 | Global Discussions
Categories
- All Categories
- 14 Welcome to the Community
- Customer Resources
- 64.9K Get Help
- 439 Global Discussions
- 138 Industry Talk
- 471 Announcements
- 4.9K Ideas & Feature Requests
- 129 Brandfolder
- 148 Just for fun
- 67 Community Job Board
- 486 Show & Tell
- 33 Member Spotlight
- 2 SmartStories
- 300 Events
- 36 Webinars
- 7.3K Forum Archives